QUAY INFRASTRUCTURE WORKS
Portonave Invests R$1 billion in the Quay Infrastructure Works
On January 5, the Terminal began adapting the quay, which requires an investment of R$1 billion to receive vessels up to 400 m in length and 17 m in breadth. The goal is to increase efficiency in cargo handling.
In the current phase, the east side (450 m) is isolated from the Terminal, with gates and temporary bridges for trucks and buses. Over 350 employees are involved in the works.
Conteúdo relacionado
Phases of the works
The execution is planned to take place in two phases. While one side of the quay is under construction (450 m), the other performs operations normally, without interruptions in activities. The works began on the east side and will proceed to the west side when this first phase is completed.

Conteúdo relacionado
Responsible Companies
The work is the responsibility of a consortium between Besix-ECB, a Belgian company with over 110 years of experience, and Empresa Construtora Brasil (ECB), founded in 1945. Besix is famous for the Burj Khalifa, while the ECB has already carried out over 250 projects in Brazil.

Latest Updates
Notícias obra do cais n° 17
27/05/2025Notícias obra do cais nº 16
30/04/2025Notícias obra do cais nº15
18/03/2025Notícias obra do cais nº14
18/02/2025Notícias obra do cais nº13
18/01/2025Notícias obra do cais nº12
13/12/2024Notícias obra do cais nº11
22/11/2024Notícias obra do cais nº10
19/10/2024Notícias obra do cais nº9
19/09/2024Notícias obra do cais nº8
17/08/2024Notícias obra do cais nº7
16/07/2024Notícias obra do cais nº6
13/06/2024Notícias obra do cais nº5
21/05/2024Notícias obra do cais nº4
10/04/2024Notícias obra do cais nº3
28/03/2024Notícias obra do cais nº2
28/02/2024Notícias obra do cais nº1
28/01/2024Notícias obra do cais nº1
28/01/2024
This newsletter complies with the condition of validity of the 5.12 Social Communication Program of the Environmental Installation License No. 66/2023, issued by the Institute of the Environment of Santa Catarina (IMA).